Stansbury Park
Observatory Complex (SPOC)
Donna Pease
Wiggins Refractor House
Exterior Work
12 OCT 2005 to 02 MAY 2011
(click on
images for enlarged view)
001

The sidewalk was poured today. 12 OCT 2005
002

Inscriptions on the building
foundation and the new sidewalk show it took about one year to finish
the building. 12 OCT 2005
|
003
|
004
|
|
|
Bruce Grim, Patrick Wiggins and Boyd McNeil digging holes for the hedge. 02 MAY 2006
005

Boyd McNeil & Bruce Grim put
one of the hedge plants in place. 02 MAY 2006
006

Roger Butz applies ground bark
around one of the newly planted hedge plants. 02 MAY 2006
007

The hedge is planted. 02 MAY 2006
008

Weed blocker material and lots of
bark were put down today. 24 MAY 2006
009

Bruce Grim adds mounting bolts to
the Refractor House sign. 15 JUN 2006
010

Patrick Wiggins drills mounting
holes for the Refractor
House sign. 15 JUN 2006
011

Patrick Wiggins makes sure the
mounting bolts fit the mounting holes before applying the cement.
15 JUN 2006
012

Noted optician John Gregory
(inventor of the Gregory-Maksutov telescope design) cements the sign in
place. 15 JUN 2006
013

The Refractor House sign in
place. 15 JUN 2006
|
014
|
015
|
|
|
The hedge 4 months after planting. New fence was installed today. 12 SEP 2006
|
016
|
017
|
|
|
Refractor House hedge as it appeared on 11 OCT 2008.
|
018
|
019
|
|
|
Roger Butz and Bruce Grim preparing to install forms between the Harmons Observatory and the Refractor House. 21 MAR 2009
020

Roger Butz and Patrick Wiggins
install forms between the
Harmons Observatory and the Refractor House. 21 MAR 2009
021

Bruce Grim and Roger Butz work on
forms between the Harmons
Observatory and the Refractor House. 21 MAR 2009
022

Bruce Grim inspects finished
forms between the Harmons
Observatory and the Refractor House. 21 MAR 2009
023

Forms for the ADA telescope pad
installed. 21 MAR 2009
|
024
|
025
|
|
|
The first concrete truck arrives. 24 MAR 2009
026

Pouring the ADA telescope pad. 24 MAR 2009 Boyd McNeil
image.
027

Bruce Grim and Patrick Wiggins
work the concrete for the ADA telescope pad. 24 MAR 2009 Boyd McNeil
image.
028

Roger Butz smooths the concrete
between the Harmans Observatory and Refractor House as Ken Harris and
Ron Ford look on. 24 MAR 2009
029

Pouring concrete between the
Harmans Observatory and Refractor House. 24 MAR 2009 Boyd McNeil
image.
030

Rodger Fry, Ken Harris and Ron
Ford spread concrete between the Harmans Observatory and Refractor
House. 24 MAR 2009 Boyd McNeil
image.
031

Rodger Fry smooths the concrete
between the Harmans Observatory and Refractor House as Ron Ford and
Roger Butz look on. 24 MAR 2009
032

Newly completed concrete section
between the Harmans Observatory and Refractor House. 02 APR 2009
033

Newly completed pad for the ADA telescope. 02 APR 2009
034

Bruce Grim waters the newly
installed sod. 13 APR 2009
035

Roger Butz lays sod. 13 APR 2009
|
036
|
037 |
|
|
Refractor House hedge as it appeared 5 years after planting. 02 MAY 2011